A project team is preparing a report for the stakeholders. The team gathers and collates a large amount of data to be included in the status report.
What should the project manager do next?
Select an option, then click Submit answer.
-
○
Ensure the team follows standard operating procedures (SOP) for creating a stakeholder report.
-
○
Instruct the team to make only a graphical representation of all the data for the report.
-
○
Instruct the team to conduct a meeting with the stakeholders before finalizing the report.
-
○
Instruct the team to analyze and interpret the data before including it in the report.