Question 16 (Volume C)

What does CPI value less than 1.0 indicates?

Select an option, then click Submit answer.

  • Cost overrun for work completed

  • Scheduled performance is great

  • Cost underrun of performance to date

  • Cost for completed work is as per estimate

Question 17 (Volume D)

In the last year, all program phase gate reviews received excellent feedback and exceeded stakeholder expectations. Recently, the customer decides that there is no need to continue phase gate reviews.

What should the program manager do next?

Select an option, then click Submit answer.

  • Ask the stakeholders what they want and proceed with their recommendations.

  • Agree with the customer and initiate change control procedures.

  • Continue periodic gate reviews to maintain program effectiveness for benefits realization.

  • Replace program reviews with periodic communications of the program's status.