Question 16

Which of the following roles is MOST involved in checking the quality of the deliverables and supporting the project manager during the project?

Select an option, then click Submit answer.

  • Sponsor

  • Team leader

  • Project coordinator

  • Tester

Question 17

A project manager is managing a project with a hard deadline in two weeks. At the current rate of progress, the project will not finish on time.

Which of the following techniques is MOST likely to be used to complete the project on time?

Select an option, then click Submit answer.

  • Throttling

  • Crashing

  • Resource leveling

  • Resource smoothing

Question 18

A project team learns that potential remodeling on the production floor might occur during the execution phase of their project. The project team starts debating the different options available to keep delivering without adjusting the schedule. Which of the following risk activities is being performed?

Select an option, then click Submit answer.

  • Mitigation

  • Quantification

  • Planning

  • Identification