Question 13

A company has determined it does not have the in-house capability to perform a project and wants to procure third-party services.

Which of the following documents will the company MOST likely release FIRST?

Select an option, then click Submit answer.

  • RFO

  • RFI

  • RFP

  • RFQ

Question 14

A customer has requested additional features for an active project.

Which of the following steps should take place NEXT?

Select an option, then click Submit answer.

  • Implement the requested changes.

  • Evaluate the impact of the changes.

  • Update all project documents.

  • Submit the requested changes to the CCB.

Question 15

During a project, the project manager discovers there is insufficient time allotted for quality control. The project manager prepared to submit a revised schedule to the CCB.

Given the attached chart, which of the following is the critical path if one day is added to each task for quality control?

Select an option, then click Submit answer.

  • 12 days

  • 16 days

  • 17 days

  • 22 days