Question 10

A project team is overseeing the installation of a new reptile habitat at the local zoo. During execution, zoo personnel decides to house a different type of reptile that will require a different temperature range than the capacity of the installed system. The modification has been approved. Which of the following constraints are MOST likely to be affected? (Choose two.)

Select all that apply, then click Submit answer.

  • Quality because the existing system is now outside the threshold.

  • Requirements because this is a change to initial scope.

  • Cost because replacing the system incurs additional expense.

  • Schedule because this was an unscheduled task and will impact the timeline.

  • Stakeholders because they will need to understand the modification and provide buy-in.

Question 11

A client has requested a project be completed ahead of schedule. The client understands the triple constraints and agrees to expand the defect tolerance.

Which of the following should the PM do NEXT?

Select an option, then click Submit answer.

  • Crash the schedule.

  • Notify the project team.

  • Initiate a change request.

  • Accept the risk.

Question 12

Upper management asks a project sponsor to provide several ad hoc reports as a brief overview of the project’s current status.

Which of the following types of reports should the project sponsor use to quickly summarize the status report data?

Select an option, then click Submit answer.

  • Pie chart

  • Run chart

  • Project schedule

  • Dashboard information