A project manager is analyzing the cost variances produced when comparing two different projects completions.

Which of the following factors could be causing the increased variance for the four-month projects? (Choose two.)
Select all that apply, then click Submit answer.
-
○
Increased resource productivity
-
○
Increased resource allocation
-
○
Increased schedule variance
-
○
Increased labor cost
-
○
Increased labor overhead