What to study for each CSITMS domain
General Requirements
Covers the foundations of NFPA 25 (2014): the scope of the standard, the property owner's retained responsibilities even when ITM is contracted out, and the requirement for qualified personnel. It also covers records and reports, providing access to components, maintaining heat against freezing, evaluating changes in occupancy or hazard, and the distinction between deficiencies and impairments.
Key skills
Applying owner responsibilities, qualifying ITM personnel, keeping auditable records, evaluating hazard changes, and classifying deficiencies versus impairments.
Inspection
Covers the visual inspection programme for sprinklers, piping, fittings, hangers, and control valves, including weekly checks of sealed valves and dry-system gauges and monthly checks of locked or supervised valves, wet-system gauges, alarm valves, and fire department connections. It also covers quarterly alarm and supervisory device inspections, annual sprinkler and piping inspections, fire pump house inspections, and the disposition of painted, corroded, or loaded sprinklers.
Key skills
Applying inspection frequencies by component, recognising conditions that require sprinkler replacement, verifying valve and gauge status, and documenting inspection findings.
Testing
Covers functional testing, including the annual main drain test and investigation of residual pressure drops over 10 percent, quarterly waterflow alarm tests through the inspector's test connection, and dry-pipe priming level and trip testing on quarterly, annual, and three-year cycles. It also covers weekly fire pump churn tests, the annual pump flow test at churn, rated, and 150 percent flows, five-year gauge and private main tests, annual antifreeze and backflow forward-flow tests, and age-based sprinkler sample testing.
Key skills
Performing and interpreting main drain, alarm, valve trip, and pump flow tests, applying test frequencies, and acting on deteriorating test results.
Maintenance
Covers keeping systems in operating condition: annual exercising and lubrication of control valves, like-for-like sprinkler replacement matching K-factor and temperature rating, and maintaining the spare sprinkler stock and wrench. It also covers resetting and internally inspecting dry valves after operation, correcting deficiencies promptly, pressure-reducing valve test cycles, antifreeze correction, diesel pump upkeep, freeze-season preparation, and restoring valves and supervision after work.
Key skills
Scheduling preventive maintenance, selecting correct replacement components, maintaining spare stock, correcting deficiencies to closure, and restoring systems fully after maintenance.
Obstruction Investigation & Impairments
Covers the five-year internal obstruction investigation, the findings that trigger one sooner, such as foreign material in tests, plugged devices, and signs of microbiologically influenced corrosion, and the flushing or cleaning that follows a confirmed obstruction. It also covers Chapter 15 impairment procedures: the impairment coordinator, the red tag system, notifications to the AHJ, fire department, alarm company, and insurer, prior authorisation of planned impairments, and evacuation or fire watch when an outage exceeds 10 hours in a 24-hour period.
Key skills
Recognising obstruction and MIC triggers, scoping an internal investigation, coordinating impairments with tagging and notification, and arranging fire watch for extended outages.