Question 10

The MRP run detected a shortage of a materila that you sorce from an external supplier in full pallets. How can you make sure you will only recive full pallets?

Select an option, then click Submit answer.

  • Use the fixed lot procedure.

  • Use the MRP type for vendor managed inventory.

  • Use the minimum order quantity

  • Use the reorder point