Showing 4–6 of 10 questions

Question 4

What are the consequences if the Dispatched operation status is set for a production order operation?

Select all that apply, then click Submit answer.

  • You can reschedule the operation using midpoint scheduling in a planning table.

  • You can reschedule the operation using finite scheduling in planning table

  • You can reschedule the operation using lead time scheduling in a planning table

  • You can reschedule the order using infinite scheduling in a planing table

Question 5

Which information is required when you created a production master in SAP S/4HANA?

Select all that apply, then click Submit answer.

  • Selective screen for views

  • Product type

  • Base unit of measure

  • Industry sector

Question 6

You want to insert an operatio at a certain time on work center. The planning direction is forward. The disired dispatching time concides with an operation that has previously been dispatched. How does the insertion take place?

Select an option, then click Submit answer.

  • The previously dispatched operation stays as is; the new operation is inserted after the the dispatched operation.

  • The previously dispatched operation stays as is; the new operation is inserted before the the dispatched operation.

  • The new operation is inserted at the desired time; the previously dispatched operation is moved forward.

  • The new operation is inserted at the desired time; the previously dispatched operation is moved backward.