C_TS422_2021 SAP Certified Application AssociateSAP S/4HANA Production Planning and Manufacturing

Loading demo links...

Showing 7–9 of 10 questions

Question 7

You have maintained the parameters for simple discontinuation in the material master of a component. Which business process will be affected if the available stock is zero and the discontinuation date is in the past?

Select an option, then click Submit answer.

  • Production order release

  • Material requirements planning

  • Backflushing

  • Kanban

Question 8

Your production planners must execute planning only for specific resources. How can you achive this in advanced Planning(PP/DS)

Select an option, then click Submit answer.

  • Use heuristic.

  • Use a resource group.

  • Use a propagation range.

  • Use a planning group.

Question 9

Which master data object governs the relationship between supply source and demand source in the Kanban process?

Select an option, then click Submit answer.

  • Control cycle

  • Production supply area

  • Replenishment strategy

  • Rate routing