Question 7

Cost & budget

A service Company use project management and they complain that the system does not prevent their project manager from

exceeding their budget.

What action do you have tsolve the problem?

Select an option, then click Submit answer.

  • Activate availability control For projects in the control area. Enter the plan data for each WBS element.

  • Activate availability control for the important WBS element. Define the tolerance limit on each WBS element.

  • Activate availability control in the assign budget profile. Defined the tolerance limit in the customizing.

  • management in the project definition. Enter the budget in the master data of the top WBS element.

  • Activate commitment

Question 8

The basic dates of subordinate WBS elements should be extrapolated without taking into account the basic dates of higher-level WBS elements. What planning method for basic dates do you use ?

Select an option, then click Submit answer.

  • Free planning

  • Top-down

  • Strict bottom-up

  • Bottom-up

Question 9

A customer project must be finished at a given due date. The project consists of WBS elements and networks. What scheduling type do you use?

Select an option, then click Submit answer.

  • Only capacity requirements

  • Forward

  • Current date

  • Backward