C_TS412_1909 SAP Certified Application AssociateSAP S/4HANA Project Systems

Loading demo links...

Showing 1–3 of 10 questions

Question 1

Resources

Which of the following transactions can you use to post actual cost for external processing.

Note : there are 2 correct answer for this question.

Select all that apply, then click Submit answer.

  • Approval of a service entry sheet

  • Posting a goods receipt

  • Creating a service entry sheet

  • Approval of a good receipt.

  • Creating a purchase order.

Question 2

You want to determine the planned costs for an internally processed activity. Which data do you need Note: There are 2 correct answers to this question

Select all that apply, then click Submit answer.

  • Duration

  • Activity type

  • Work

  • Profit center

Question 3

Which of the following is visible in the project planning board? Note: There are 2 correct answers to this question

Select all that apply, then click Submit answer.

  • Project-relevant purchase orders

  • Capacity requirements

  • Maintenance orders assigned to an activity

  • Production orders assigned to WBS elements