Question 4

What are the prerequisites for delivering materials from the project? Note: There are 2 correct answers to this question

Select all that apply, then click Submit answer.

  • A delivery document type must be configured

  • A sold to party is necessary

  • A shipping point is necessary

  • A sales order must be created in advance

Question 5

Materials

Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set

of dates that can be scheduled.

Which set of dates can be used for scheduled for network?

Note : there are 2 correct answer for this question.

Select all that apply, then click Submit answer.

  • Planned dates

  • Fundamental dates

  • Basic dates

  • Baseline dates

  • Forecast dates

Question 6

Project Structures

You want to enable user fields for customer project. Therefore you create several field keys. What is the benefit of assigning a field key to the project profile?

Select an option, then click Submit answer.

  • The field key is the default value for the WBS element and the activities too.

  • The tab user fields is invisible.

  • The field key is hard coded in the WBS element.

  • The field key is the default value only for the WBS element.