Question 13 (Volume B)

Which is a valid statement about the Project Support role?

Select an option, then click Submit answer.

  • Can be performed by the Project Manager

  • Is an optional role for a PRINCE2 project

  • Produces Checkpoint Reports for the Project Manager

  • Can be combined with the Project Assurance role

Question 14 (Volume A)

Which role is responsible for the management of a risk assigned to it?

Select an option, then click Submit answer.

  • Project Support

  • Risk owner

  • Risk actionee

  • Project Assurance

Question 15 (Volume B)

What should influence the Project Board's decision whether to delegate its Project Assurance responsibilities?

Select an option, then click Submit answer.

  • The preference of the Project Manager

  • Having insufficient authority to perform the role

  • Having insufficient time to perform the role

  • The need to involve key stakeholders on the project management team