Question 7 (Volume B)

During the Initiating a Project process, which product is updated to incorporate the estimated time and costs from the Project Plan?

Select an option, then click Submit answer.

  • Project Product Description

  • Business Case

  • Project Brief

  • Project mandate

Question 8 (Volume A)

What is the definition of a project outcome?

Select an option, then click Submit answer.

  • A measurable improvement that is perceived as an advantage by one or more stakeholders

  • The reason for the project

  • The result of the change derived from using the project's outputs

  • The project's specialist products.

Question 9 (Volume C)

Which is a purpose of the Directing a Project process?

Select an option, then click Submit answer.

  • Create and authorize the project mandate

  • Ensure that work on products allocated to the team is authorized and agreed

  • Control the day-to-day running of the project