Question 10 (Volume A)

Which statement describes the responsibilities of a risk actionee?

Select an option, then click Submit answer.

  • Identifying risks to the project that might occur in their department

  • Owning and authorizing the use of the risk budget to fund risk responses

  • Managing, monitoring and controlling of all aspects of an assigned risk

  • Carrying out a risk response action to respond to a particular risk

Question 11 (Volume B)

How is a Benefits Review Plan used in the Closing a Project process?

Select an option, then click Submit answer.

  • Checked for inclusion of activities to confirm those benefits which cannot be measured until after project closure

  • To capture the baseline measures against which to assess benefits

  • To capture side-effects (beneficial or adverse) identified during post-project benefits reviews

  • To gain approval for the post-project activities and transfer responsibility to corporate or programme management

Question 12 (Volume B)

In what product should the quality criteria for a specialist product be recorded?

Select an option, then click Submit answer.

  • Quality Management Strategy

  • Quality Register

  • Product Description