PRINCE2-Practitioner PRINCE2 Practitioner

Loading demo links...

Showing 10–12 of 15 questions

Question 10 (Case Study 4)

The e-learning course is being delivered by an external consultancy. The consultancy wants to grow its e-learning business and use this project as an opportunity to demonstrate its skills in this area. They have asked ABC Company if they can publish a testimonial from ABC Company on their website following successful completion of the Health and Safety Training Project. A representative from the external consultancy has been invited to act as senior supplier on the Health and Safety Training project board.

Is this an appropriate action for the 'defined roles and responsibilities' principle, and why?

Select an option, then click Submit answer.

  • Yes, because the supplier interest needs to be represented on the Health and Safety Training project board

  • Yes, because the supplier needs to demonstrate its skills in e-learning to grow its business

  • No, because the supplier needs to demonstrate its skills in e-learning to grow its business

  • No. because the supplier needs to publicize the success of the project on their website

Question 11 (Mixed Questions)

Which of the following statements are True:

1. Quality management is the complete set of quality standards, procedures and responsibilities for a site or organization.

2. Quality planning is about defining products required of the project with their respective quality criteria, methods and responsibilities.3. Quality control focuses on the operational techniques and activities used to carry out quality inspections

4. Quality assurance ensures that quality methods are being correctly followed.

Select an option, then click Submit answer.

  • 1, 2 & 3

  • 1, 3 & 4

  • 1, 2 & 4

  • 2, 3 & 4

Question 12 (Mixed Questions)

Who is responsible for ensuring that the value-for-money solution is constantly reassessed?

Select an option, then click Submit answer.

  • Business Assurance

  • Senior User

  • Corporate or Programme Management

  • Reject Support