Showing 7–9 of 15 questions

Question 7 (Case Study 5)

Which 2 statements explain why the Purchasing Manager should be appointed as a Senior Supplier for this project?

Select all that apply, then click Submit answer.

  • He is responsible for the organization's procurement activates.

  • He is responsible for the performance of supplier contracts.

  • He was an engineer and worked in that area before taking up his current position.

  • He can influence the external supplier's Business Case.

  • He is not appropriate for the role of Executive or Senior User.

Question 8 (Case Study 2)

Which 2 statements should be recorded under the Costs heading?

Select all that apply, then click Submit answer.

  • The MNO marketing budget this year is £120k.

  • The project will be funded from the business marketing budget

  • 10 further orders with an average profit of £2k will deliver a benefit of £20k in the first year.

  • The new company logo is estimated to cost £4k.

  • Project costs are estimated to be a total of £26.5k.

Question 9 (Case Study 3)

Which 2 statements should be recorded under the Major risks heading?

Select all that apply, then click Submit answer.

  • Due to market conditions a suitable service provider may not be found, possibly leading to premature closure of the project.

  • Owing to employment contract changes staff may resist outsourcing, which would make it difficult to transfer staff to the selected service provider.

  • MFH's operations may be reduced and the 1a-year contract may not achieve its estimated value of £80m, which would reduce the service provider's profit.

  • The initial estimates, taken from the feasibility study report, indicate that the project will take two years to complete, which means that the business problems would remain for this period.

  • The management stages recommended by the consultants may not be appropriate, resulting in confusion in planning.