Question 10 (Volume D)

Analogous cost estimating relies on which of the following techniques?

Select an option, then click Submit answer.

  • Expert judgment

  • Project management software

  • Vendor bid analysis

  • Reserve analysis

Question 11 (Volume C)

Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?

Select an option, then click Submit answer.

  • Cost management plan

  • Quality management plan

  • Communications management plan

  • Risk management plan

Question 12 (Volume B)

Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (VVBS) to give structure to the decomposition of the scope?

Select an option, then click Submit answer.

  • Activity network diagrams

  • Affinity diagrams

  • Matrix diagrams

  • Interrelationship digraphs