Question 4 (Volume C)

When can pre-assignment of project team members occur?

Select an option, then click Submit answer.

  • When the project uses capital expenditures

  • When the required staff can be acquired from outside sources

  • When the project would be ignored due to travel expenses

  • When the project is the result of specific people being promised as part of a competitive proposal

Question 5 (Volume A)

Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?

Select an option, then click Submit answer.

  • Nominal group technique

  • Idea/mind mapping

  • Affinity diagram

  • Brainstorming

Question 6 (Volume B)

The scope management plan and scope baseline are contained in:

Select an option, then click Submit answer.

  • organizational process assets

  • a requirements traceability matrix

  • the project charter

  • the project management plan