Which of the following is a project constraint?
Select an option, then click Submit answer.
-
○
Twenty-five percent staff turnover is expecteD.
-
○
The technology to be used is cutting-edgE.
-
○
Project leadership may change due to volatile political environment.
-
○
The product is needed in 250 days.