Question 19 (Volume A)

Which of the following components is included in a transition plan?

Select an option, then click Submit answer.

  • Ownership

  • Quality metrics

  • Project budget

  • Quality baseline

Question 20 (Volume C)

Which of the following should a project manger do to actively track issues as they are identified?

Select an option, then click Submit answer.

  • Develop a quality management plan.

  • Create a process for anonymous team review of issue resolution.

  • Make an issues log template.

  • Update the issues log.