JK0-017 CompTIA E2C Project+ Certification Exam

Loading demo links...

Showing 4–6 of 20 questions

Question 4 (Volume B)

Which of the following is true of a work breakdown structure (WBS)? (Select Two).

Select all that apply, then click Submit answer.

  • It consists of work packages at the top level which are decomposed to increasingly detailed levels.

  • It is a quantitative analysis tool used in quality management to analyze defects.

  • Each descending level represents an increasing detailed definition of the project work.

  • It is developed during the planning process and used to create the project scope statement.

  • It organizes and defines the total scope of the project.

Question 5 (Volume A)

Which of the following are created using information contained in the work breakdown structure (WBS)? (Select Two).

Select all that apply, then click Submit answer.

  • Project scope statement

  • Project statement of work

  • Project charter

  • Project activity estimates

  • Project resource estimates

Question 6 (Volume D)

Which of the following would be included in a project scope document? (Select Two).

Select all that apply, then click Submit answer.

  • Project constraints

  • WBS dictionary

  • Project assumptions

  • Project charter

  • Work Breakdown Structure (WBS)