Question 10

A software development program will launch iterative versions of new software called Alpha over two years Following that, a program will be released to the program team and developers to create new software called Beta While the program manager prepares the program closure plan tor Alpha, the program sponsor expresses concern about its support after program closure.

What should the program manager do as part of Alpha's program closure plan?

Select an option, then click Submit answer.

  • Execute the transition plan and Include Knowledge transfer to transition Alpha support to operations

  • Keep the Alpha program open until support is no longer required, then execute program closure

  • Adjust Alpha's exit criteria to ensure its support is included in the Beta program

  • Document the program closure procedure to ensure that resources are released from Alpha to develop Beta

Question 11

A program is midway through the program delivery phase when a key stakeholder asks if the program is meeting its defined objectives.

How should the program manager demonstrate the program's progress"?

Select an option, then click Submit answer.

  • Define the key performance indicators (KPIs) for the program's outcome

  • Invite the key stakeholder to review the program charter and the program objectives

  • Provide additional program performance reports to the key stakeholder

  • Maintain the benefits register and provide it to the key stakeholder

Question 12

A program manager is responsible for constructing a USS50 million building Management suggests it will take three years to complete The program manager can select a design-build option to optimize the construction schedule to 1 5 years However heavy demand for steel is causing price increases and delivery delays. II this trend continues, it could take as long as 4.5 years to complete construction. You learn that a new technology can yield a definitive delivery schedule of 1 25 years

What is the expected time of delivery?

Select an option, then click Submit answer.

  • 1.25 years

  • 1 50 years

  • 175 years

  • 1 00 years