Question 7

Which two of the following documents MUST be submitted by the communication's project contractor for review and approval? {Select two options.)

Select all that apply, then click Submit answer.

  • Test reports

  • Shop drawings

  • Cost summary

  • Site survey

  • Request for information (RFI)

Question 8

When estimating an ICT distribution designer project timeline schedule based on the scope of work which two scheduling methods use network diagrams lo integrate logical activities and identify critical paths on the project? (Select two options.)

Select all that apply, then click Submit answer.

  • If This Then That (IFTT)

  • Gantt Chart

  • Work Breakdown Structure (WBS)

  • Critical Path Method (CPM)

  • Program Evaluation Review Technique (PERT)

Question 9

An ICT distribution designer is preparing a price quote for a building design with multiple floors originally sized at 40.000 ft (3716 m2). While the designer is preparing the quote, the structural engineer indicates the building has been increased in size to accommodate an additional 40,000 ft2 (3716 m3) per floor. The designer's recommendation to the engineer will be to increase the slot area by_____for each additional 40,000 ft3 (3716 m2)

Select an option, then click Submit answer.

  • 0.006 m2 (8 in2)

  • 0.008 m2 (12 in2)

  • 0.040 m2 (60 in3)

  • 0.60 m2 (80 in3)