RCDDv14 BICSI Registered Communications Distribution Designer –

Loading demo links...

Showing 4–6 of 15 questions

Question 4

Which two of the following are ADVANTAGES of underground conduit systems? (Select two options.)

Select all that apply, then click Submit answer.

  • Provide additional physical cable protection

  • Not adaptable for future facility placement or removal without disturbing the property

  • Economical over a long life

  • Require more installation time than aerial or direct-buried installations

  • Route planning is not as critical as aerial or direct-burial

Question 5

A project's installation start involves a Kickoff Meeting and the General Contractor's Coordination Meeting. As part of the designer's responsibilities, which two of the following ate key elements of the Kick-off Meeting? (Select two options.)

Select all that apply, then click Submit answer.

  • Project submittal approval process

  • RFI process

  • Payment procedures

  • Punch List process

  • Project start and completion dates

Question 6

Which two of the following are included in the ICT distribution designer's role of vendor and contractor coordination'? (Select two options.)

Select all that apply, then click Submit answer.

  • Conduct final ICT inspections to ensure standard and code compliance, design intent, and/or client requirements are met.

  • Monitor project schedule for delays

  • Produce ICT closeout documentation for the owner to provide the record documentation of the installation

  • Communicate status to stakeholders

  • Assist in the resolution of unforeseen conditions, change orders. RFIs, and changes to the project's critical path