Question 13

A country is in the process of strengthening its defense program. A key project is not meeting its specified performance objectives. The project manager initiates a change request to address this issue.

What should the program manager do NEXT?

Select an option, then click Submit answer.

  • Consider the option to close out the key project

  • Evaluate the program and re-baseline the objectives

  • Assess the benefits and impact to the program.

  • Amend the risk register with the key project changes

Question 14

What actions are taken in the process of developing and maintaining a program risk register?

Select an option, then click Submit answer.

  • Assign ownership of risks with appropriate responsibilities, document agreed-upon response strategies and provide the foundation for the risk management plan

  • Assign ownership of risks with appropriate responsibilities, document agreed-upon response strategies and identify the root cause of potential risks

  • Assign ownership of risks with appropriate responsibilities, document agreed-upon response strategies, and proactively manage program issues

  • Assign ownership of risks with appropriate responsibilities, document agreed-upon response strategies, and identify residual risks.

Question 15

A company initiates a program to reorganize its sales and production departments. Three production departments are located at the three production plants next to the company's headquarters Five regional sales departments are located at different locations around the world.

At this stage of the program, what is the first step?

Select an option, then click Submit answer.

  • Develop a program work breakdown structure

  • Identify and quantify business benefits of the program

  • Determine and prioritize the various components of the program

  • Prepare a program organization chart covering both sales and production