Question 7

In specifying labels and pruned tags that meet Underwriters Laboratories (UL) 969 Standard, marking and labeling systems are provided following the listed metrics. Which two of the following are REQUIRED for the UL standard? (Select two options.)

Select all that apply, then click Submit answer.

  • Adhesion test

  • Thickness test

  • Texture test

  • Durability test

  • Visual inspection

Question 8

The type of apparatus housed in ERs vary greatly in size, purpose and function. Which two of the following active equipment is included? (Choose two.)

Select all that apply, then click Submit answer.

  • Cross-connect facilities

  • Telecommunications equipment

  • Environmental controls

  • Lighting controls

  • Building system equipment

Question 9

In the last year, all program phase gate reviews received excellent feedback and exceeded stakeholder expectations recently, the customer decides that there is no need to continue phase gate reviews.

What should the program manager do next?

Select an option, then click Submit answer.

  • Ask the stakeholders what they want and proceed with their recommendations

  • Agree with the customer and Initiate change control procedures

  • Continue periodic gate reviews to maintain program effectiveness for benefits realization

  • Replace program reviews with periodic communications of the program's status