Your production planners are allowed to execute planning only for specific resources. How can you achieve this in Advanced Planning (PP/DS)?
Select an option, then click Submit answer.
Reference / correct answer:
Most accepted answer: A. Use a planning area.
Community votes: A=1
Selected Answer: A In PP/DS, **Planning Area** is a permission control function that defines the scope of materials, resources, plants, etc., and restricts a specific worker to perform planning only for resources included in the area. Officially, this function is provided and is a permission-based planning restriction method. upvoted 1 times