SIMULATION
Fill in the blank with the appropriate word. When activities are logically linked, they become the __________
Answer is in the explanation below.
Loading demo links...
Showing 1–15 of 15 questions
SIMULATION
Fill in the blank with the appropriate word. When activities are logically linked, they become the __________
Answer is in the explanation below.
You work as a project manager for Honeywell Inc. You have been distributing performance information, including status reports, progress measurement, and forecasts to various stakeholders. A trainee of this company wants to know what are the inputs for generating performance reports. Which of the following are the necessary inputs? Each correct answer represents a part of the solution. Choose two.
Select all that apply, then click Submit answer.
Variance analysis
WPM
WPI
Change request
Which of the following characteristics of conflict and the conflict management process should be recognized by the project managers while handling conflict in a team environment? Each correct answer represents a complete solution. Choose all that apply.
Select all that apply, then click Submit answer.
Conflict resolution should focus on issues, not personalities.
Conflict is natural and forces a search for alternatives.
Openness resolves conflict.
Conflict is an individual issue.
John works as the project manager for Blue Well Inc. He is identifying the phases within the scope of work for the project plan. Which of the following can be categorized as a project phase? Each correct answer represents a complete solution. Choose all that apply.
Select all that apply, then click Submit answer.
Concrete
Pre-construction
Engineering
Conceptual engineering
John is a scheduler in ABC Company. He has to plan an activity for the schedule models. Which of the following activities will he use to make the schedule models? . Each correct answer represents a complete solution. Choose all that apply.
Select all that apply, then click Submit answer.
Hammocks
Critical path scheduling
Flags
Tasks
Jenny is the project manager for her organization. Her project is not doing well on project schedule performance, and management wants her to predict how the project schedule and cost will end.
Management has asked Jenny to report and forecast her project's performance based on the Judgmental methods. Which of the following judgmental methods will Jenny use to accomplish the task? Each correct answer represents a complete solution. Choose all that apply.
Select all that apply, then click Submit answer.
Forecast by analogy
Technology forecasting
Autoregressive moving average
Scenario building
Tom works as the project manager for BlueWell Inc. He spends the majority of his time communicating with team members and the project stakeholders. Various communication skills are involved in the communication processes. Which communication skills are involved in this process? Each correct answer represents a part of the solution. Choose all that apply.
Select all that apply, then click Submit answer.
Internal and External
Vertical and Horizontal
Confronting and problem solving
Formal and Informal
Which of the following are the outputs to the Determine Budget process? Each correct answer represents a complete solution. Choose all that apply.
Select all that apply, then click Submit answer.
Project document updates
Scope baseline
Cost performance baseline
Project funding requirements
You are the project manager for your organization. You are managing a project to create new software for your clients. During the project execution, there have been some unforeseen delays that will require your attention. You will need four inputs to the control schedule process. Which of the following documents would not be an input for the control schedule process?
Select an option, then click Submit answer.
Project schedule
Work performance information
Project management plan
Earned value management results
You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned and they'd like to know what your schedule variance is. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450. What is the schedule variance for this project?
Select an option, then click Submit answer.
-$45,789
-$56,790
There is not enough information to know.
-$30,268
Sam is the project manager of the NQQ project. He and the project team have completed the stakeholder identification process for his project. What is the main output of the identify stakeholders process?
Select an option, then click Submit answer.
Communications management plan
Stakeholder register
Requirements
Stakeholder management strategy
Harry works as a project manager for BlueWell Inc. A risk that has been identified and analyzed in the project planning processes is now coming into fruition. Who among the following is responsible for implementing the risk responses or contingency plan?
Select an option, then click Submit answer.
Risk owner
Harry
Project sponsor
Subject matter expert
Which organizational theory explains the factors that promote performance of people in any organization?
Select an option, then click Submit answer.
Herzberg's theory
Maslow's Hierarchy theory
McGregor's theory
Expectancy theory
Holly is the project manager for her organization. Her current project is running late and her project customer has asked Holly to find a method to apply corrective actions to the project schedule. Holly is exploring the concept of crashing the project. Which of the following statements is true about crashing the activities in Holly's project?
Select an option, then click Submit answer.
The activities to be crashed must have additional quality control metrics associated with them.
The activities to be crashed cannot be of fixed duration.
The activities to be crashed cannot have risks associated with them greater than 0.80.
The activities cannot be on the critical path in order to be crashed.
Joe is the project manager of the HJN Project. Joe's project is a renovation of an office building. There must be 30 hours between the painting activity and the carpet activity in the project schedule to eliminate the risk of wet paint getting on the carpet. What is the best approach Joe can do to alleviate this issue?
Select an option, then click Submit answer.
Add lead time to the painting activity.
Change the relationship of the carpet activity and the painting activity to finish-to-finish.
Create a dummy activity between the painting activity and the carpet activity for the duration of the drying process.
Add lag time to the carpet activity.
This free practice test covers the PMI Scheduling Professional (PMI-SP) exam from PMI. The 15 questions are a free sample of the full Study4Pass practice set of 320 questions, so you can check your level before you commit to the real exam. The free sample includes 7 single-answer, 7 multiple-answer and 1 hands-on lab questions — the same mix of formats you will meet in the full set. Questions are spread across the areas that matter most on the real exam: Project Management Framework, Scheduling, Risk Management and Resource Management. The PMI Scheduling Professional (PMI-SP)® is a certification exam offered by the Project Management Institute (PMI).
The target audience of the PMI PMI-SP Exam is project managers who have experience with project scheduling and who wish to become certified as a PMI Scheduling Professional (PMI-SP). The PMI-SP exam requires applicants to have a minimum of 2,000 hours of project scheduling experience and 23 contact hours of project scheduling education.
Treat this sample as a diagnostic. Answer honestly, check the explanation after every question, and note which topics feel shaky. A short, focused review of those topics is worth more than re-reading everything — and the full set lets you drill them topic by topic.
A good way to use this page: take the whole sample in one sitting, then go back over every explanation with fresh eyes. Mark the topics that felt uncertain, not just the ones you got wrong — uncertain answers are unmarked risk on the real exam. One or two focused passes like this usually move a score more than days of passive reading.
Inside the full PMI-SP practice set:
Answer a question, then check the result to see the correct answer and the explanation behind it. Work at your own pace — there is no timer and no signup. Stuck on a concept? This is an AI-Enabled practice test: use Ask AI on any question and get the underlying concept explained in plain words, so you learn the reasoning instead of memorizing answers. Ready for more? The full 320-question set adds a timed Exam Simulation mode, topic training for your weak areas, and a flagged-question review, so you can practise the way the real exam feels.
Yes — the 15 questions on this page are completely free, with no signup and no payment details needed.
320 questions. The 15 free questions above are a sample of that full set, in the same style and topic balance.
Yes — every question shows the correct answer with an explanation, and Ask AI can explain the concept behind a question in plain words if you want to go deeper.
No. This is a practice test: the questions are written to mirror the real PMI-SP exam’s topics and difficulty, not copied from it.