The first step in developing a commissioning protocol for a new PV system is to:
Select an option, then click Submit answer.
- ○ Review the design documents, equipment manuals and applicable codes to define what must be tested and the acceptance criteria
- ○ Copy a protocol from an unrelated wind project
- ○ Ask the owner what tests they would like
- ○ Energise the system and see if it produces power