PSM-II Professional Scrum Master level II (PSM II)

Loading demo links...

Showing 7–9 of 10 questions

Question 7

If there are multiple Scrum Teams working on the same product, all of the Scrum Teams must mutually define a Definition of Ready (DoR). The DoR is a checklist that the Product Owner must fulfill before a Product Backlog item can be presented at the Sprint Planning. This protects the Development Team from interruptions and disruptions during the Sprint.

Select an option, then click Submit answer.

  • True

  • False

Question 8

Which approach would you recommend to ensure that the Product Backlog items discussed at Sprint Planning are well understood, actionable, and easier to forecast?

Select an option, then click Submit answer.

  • Having a separate group of business analysts and functional testers analyzing high-ordered Product Backlog items before Sprint Planning.

  • Having the Product Owner work with stakeholders between the end of the last Sprint and before beginning the next to prepare the Product Backlog items so not to interrupt the Development Team.

  • Having the business analysts in the Development Team create the upcoming Product Backlog items during a Sprint and adding them to the next Sprint’s forecast.

  • Having the Development Team use some time during each Sprint to help the Product Owner analyze, estimate, and design items at the top of the Product Backlog that is projected to be worked on in the upcoming Sprint.

Question 9

Part of the team’s Definition of “Done” requires creating or updating technical documentation in order to maintain the product and/or features in the future. The team’s technical writer will be on vacation during the Sprint.

What should you do?

Select an option, then click Submit answer.

  • Encourage the technical writers from other teams to form a specialized team to organize and plan the work for multiple teams.

  • The Development Team members will write it as they are still responsible for creating the documentation to make the Increment done in conformance with their Definition of “Done.”

  • Wait until the technical writer returns before continuing with related items.

  • Complete all development work first while adding technical documentation to the Product Backlog to be done in a subsequent Sprint.