Question 7

Which of the following services are appropriate for a Scrum Master in regard to the Daily Scrum?

Select an option, then click Submit answer.

  • Lead the discussions of the Development Team.

  • Make sure that all 3 questions have been answered by each member of the team.

  • Keep track of whether each team member has a chance to speak.

  • Teach the Development Team to keep the Daily Scrum within the 15 minute time-box.

  • All of the above.

Question 8

The Product Owner determines how many Product Backlog items the Development Team selects for a Sprint.

Select an option, then click Submit answer.

  • False.

  • True, accordingly to what was committed to the stakeholders.

  • True, but only after confirmation by the resource manager that the Team has enough capacity.

  • True.

  • False, the Scrum Master does that.

  • False, capacity and commitment are the Project manager’s responsibility.

Question 9

User documentation is part of your definition of “Done”. However, there aren't enough technical writers for all teams. Your Development Team doesn't have a technical writer. What should you do?

Select an option, then click Submit answer.

  • Form a separate team of technical writers that will work on an on-demand basis for the various Product Owners. Work order will be first in, first out.

  • Let the user documentation remain undone and accumulate until after the last development Sprint. It will then be done by any available technical writers.

  • Wait until you have a technical writer on your Development Team to take care of this.

  • Your Development Team is still responsible for creating user documentation. In this case, the Development Team members will write it.