How can you determine the labor activities to calculate the planned duration for activities in the warehouse? Note: There are 2 correct answers to this question.
Select all that apply, then click Submit answer.
-
○
Directly
-
○
As a standard step
-
○
Using a decision service in BRFplus
-
○
Using a work step sequence