Question 10
The maintenance engineer creates a strategy plan with the call object maintenance order. Shift factors are set to 100%. Which date is relevant for the calculation of future planned dates if the maintenance work is delayed?
Select an option, then click Submit answer.
-
○
Technical completion date of the maintenance order
-
○
Date of the final time confirmation
-
○
Planned end date of the maintenance order
-
○
Planned date of the next call, independent of maintenance orderdates