Which statements regarding a maintenance order with status RELare correct? Note: There are 3 correct answers to this question.
Select all that apply, then click Submit answer.
-
○
The planner can change estimated costs only at header level.
-
○
Shop papers can only be printed after the order release.
-
○
Goods receipts for external services can be entered.
-
○
The controller can determine actual cost surcharges.
-
○
The planner can change planned costs at operation level.