Question 10

The maintenance engineer creates a strategy plan with the call object maintenance order. Shift factors are set to 100%. Which date is relevant for the calculation of future planned dates if the maintenance work is delayed?

Select an option, then click Submit answer.

  • ○

    Technical completion date of the maintenance order

  • ○

    Date of the final time confirmation

  • ○

    Planned end date of the maintenance order

  • ○

    Planned date of the next call, independent of maintenance orderdates