C_ACTIVATE05 SAP Certified Associate - SAP Activate Project Manager

Loading demo links...

Showing 7–9 of 10 questions

Question 7

What is a difference between the SAP Activate methodology for a new implementation of SAP S/4HANA cloud edition and a new implementation of SAP S/4HANA on-premise?

Please choose the correct answer. Response:

Select an option, then click Submit answer.

  • For the cloud edition, there is an additional work stream for integration with on-premise systems

  • For the cloud edition, there is an additional Q-Gate for integration with on-premise systems

  • For on-premise, there is an additional Q-Gate for system installation

  • For on-premise, there are additional deliverables for the system setup


Question 8

What does SAP Activate recommend to keep team members informed and aligned?

Please choose the correct answer. Response:

Select an option, then click Submit answer.

  • Daily status meeting with project manager

  • Daily team stand-up meeting

  • Daily e-mail status updates to project manager

  • Daily progress review meeting with sponsor


Question 9

What is a deliverable of the Application. Customer Team Enablement work stream in the Prepare phase of SAP Activate?

Please choose the correct answer. Response:

Select an option, then click Submit answer.

  • Project Charter

  • Project Documentation

  • Knowledge transfer to end users

  • Learning plan