C_ACTIVATE05 SAP Certified Associate - SAP Activate Project Manager

Loading demo links...

Showing 4–6 of 10 questions

Question 4

Which of the following tasks are required in the Prepare Phase?

There are 3 correct answers to this question. Response:

Select all that apply, then click Submit answer.

  • Train the project team

  • Set up the infrastructure to support the project

  • Define the communication plan

  • Approve the test strategy

  • Identify relevant SAP Best Practices


Question 5

What are the responsibilities of the Product Owner in release and sprint planning?

There are 2 correct answers to this question. Response:

Select all that apply, then click Submit answer.

  • Analyze the functional and technical dependencies between the user stories

  • Define objectives for each release

  • Prioritize backlog user stories by business priority

  • Estimate the backlog user stories


Question 6

What information does the product team need so that they can estimate the relative size of backlog user story correctly?

Please choose the correct answer. Response:

Select an option, then click Submit answer.

  • Available project resources

  • Test strategy

  • Definition of Done

  • Overall project schedule