Question 16 (Exam Set B)

A project team is preparing a report for the stakeholders. The team gathers and collates a large amount of data to be included in the status report.

What should the project manager do next?

Select an option, then click Submit answer.

  • ○

    Ensure the team follows standard operating procedures (SOP) for creating a stakeholder report.

  • ○

    Instruct the team to make only a graphical representation of all the data for the report.

  • ○

    Instruct the team to conduct a meeting with the stakeholders before finalizing the report.

  • ○

    Instruct the team to analyze and interpret the data before including it in the report.

Question 17 (Exam Set A)

Project stakeholders are engaged in a discussion on how to achieve the best user experience in the design of a new

application. The agile team is divided on the approach. The conflict is more of a collective disagreement than an

outright conflict.

What should the project manager do next?

Select an option, then click Submit answer.

  • ○

    Apply appropriate conflict resolution techniques to solve the issue.

  • ○

    Call a team meeting to have a formal discussion of the issue.

  • ○

    Allow the team to work through it on their own unless help is needed.

  • ○

    Engage in individual conversation with each team member.

Question 18 (Exam Set C)

A project manager schedules virtual daily standup meetings for a project, but half of the team members regularly join late or miss the meeting all together. What should the project manager do?

Select an option, then click Submit answer.

  • ○

    Discuss ground rules with the team that will include daily meetings.

  • ○

    Use one-to-one virtual meetings because they are more efficient.

  • ○

    Ask senior management for coaching regarding this situation.

  • ○

    Agree on a new time and reschedule the daily standups.