What is the relationship between the competencies required (or a PMO professional, and the PMO functions?
Select an option, then click Submit answer.
-
○
All competencies identified in the PMO VALUE RING methodology are Important for all PMO
functions, and all PMO professionals must develop them in a balanced way. - ○ Each PMO function will require different competencies, among those Identified In the PMO VALUE RING methodology. Some of them may or may not be necessary.
- ○ All the competencies Identified in the PMO VALUE RING methodology are important for all PMO functions, but with different relevance for each function.
-
○
Each function will require technical and behavioral skills, which must be present in all professionals working in the PMO.