PMI-SP PMI Scheduling Professional Practice Test

Loading demo links...

Showing 13–15 of 15 questions

Question 13 (Volume A)

Which organizational theory explains the factors that promote performance of people in any organization?

Select an option, then click Submit answer.

  • Herzberg's theory

  • Maslow's Hierarchy theory

  • McGregor's theory

  • Expectancy theory

Question 14 (Volume B)

Holly is the project manager for her organization. Her current project is running late and her project customer has asked Holly to find a method to apply corrective actions to the project schedule. Holly is exploring the concept of crashing the project. Which of the following statements is true about crashing the activities in Holly's project?

Select an option, then click Submit answer.

  • The activities to be crashed must have additional quality control metrics associated with them.

  • The activities to be crashed cannot be of fixed duration.

  • The activities to be crashed cannot have risks associated with them greater than 0.80.

  • The activities cannot be on the critical path in order to be crashed.

Question 15 (Volume B)

Joe is the project manager of the HJN Project. Joe's project is a renovation of an office building. There must be 30 hours between the painting activity and the carpet activity in the project schedule to eliminate the risk of wet paint getting on the carpet. What is the best approach Joe can do to alleviate this issue?

Select an option, then click Submit answer.

  • Add lead time to the painting activity.

  • Change the relationship of the carpet activity and the painting activity to finish-to-finish.

  • Create a dummy activity between the painting activity and the carpet activity for the duration of the drying process.

  • Add lag time to the carpet activity.