You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned and they'd like to know what your schedule variance is. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450. What is the schedule variance for this project?
Select an option, then click Submit answer.
-
○
-$45,789
-
○
-$56,790
-
○
There is not enough information to know.
-
○
-$30,268