Testing on a project has been completed. In order to proceed with deployment, a decision is needed.
Who should the business analyst contact to review the testing results and get approval to proceed with deployment?
Select an option, then click Submit answer.
-
○
The tester identified in the testing strategy
-
○
The project manager identified in the project charter.
-
○
The project sponsor identified in the scope document.
-
○
The person identified in the RACI matrix.