A project’s requirements baseline is established and approved. A stakeholder then submits a new requirement through the change control process.
How can the business analyst determine the impact on existing requirements?
Select an option, then click Submit answer.
-
○
Use time-boxing to defer the new requirement.
-
○
Review the requirements traceability matrix.
-
○
Update the use case documentation.
-
○
Perform a stakeholder analysis