PMI-PBA PMI Professional in Business Analysis

Loading demo links...

Showing 1–3 of 10 questions

Question 1

A project’s requirements baseline is established and approved. A stakeholder then submits a new requirement through the change control process.

How can the business analyst determine the impact on existing requirements?

Select an option, then click Submit answer.

  • Use time-boxing to defer the new requirement.

  • Review the requirements traceability matrix.

  • Update the use case documentation.

  • Perform a stakeholder analysis

Question 2

A business analyst has been assigned to a project team that is redesigning the company’s website. The business analyst has been documenting the relationships between requirements and has found requirements that do not trace to a business need.

Which type of requirements are these?

Select an option, then click Submit answer.

  • Tested

  • Out-of-scope

  • Implemented

  • In-scope

Question 3

A business analyst has been assigned to a project to implement a new phone system for a customer call center. The business analyst will need to create a business case.

Which of the following components will the business analyst use as input to the business case?

Select an option, then click Submit answer.

  • Product scope

  • Work breakdown structure

  • Project timeline

  • Project scope