Question 16

The product owner wants to build security firewalls into the product.

How can the team members support this?

Select an option, then click Submit answer.

  • Add new security features to the backlog and prioritize.

  • Execute a spike to research security features for the project.

  • Ask questions to determine where and how the product owner wants to use the product.

  • Ask questions to determine if the product owner can define the desired level of security.

Question 17

On what should Agile estimates be based?

Select an option, then click Submit answer.

  • A Work Breakdown Structure (WBS) from each iteration aligned with the project management plan

  • A disciplined iteration schedule, which improves predictability, combined with reaction to changes

  • Ball park figures collected from past Agile projects with scopes similar to the current project

  • Initial resource breakdown based on the available person days in the full project duration

Question 18

A product owner for two highly visible projects spends a great deal of time meeting with and reporting to senior stakeholders. The product owner is overwhelmed because both project teams request clarification on the requirements and the overall priorities.

What should the agile project manager do?

Select an option, then click Submit answer.

  • Provide both project teams with the highest priority needs

  • Request the project teams’ questions in writing prior to the next meeting

  • Facilitate a meeting with each team and the product owner to find a solution

  • Provide both teams with each project’s documentation