PMI-ACP PMI Agile Certified Practitioner

Loading demo links...

Showing 10–12 of 20 questions

Question 10

Identify all members of a Scrum Team: (Choose three.)

Select all that apply, then click Submit answer.

  • Customer

  • Stakeholder

  • Product Owner

  • Scrum Master

  • Project Manager

  • Development Team

Question 11

Extreme Programming (XP) includes which of the following practices? (Choose three.)

Select all that apply, then click Submit answer.

  • Simple Design

  • Coding standards

  • Mange WIP

  • Sustainable Pace

  • Eliminate Waste

Question 12

Which three criteria should be looked at when setting iteration length?

Select an option, then click Submit answer.

  • Time needed to complete a user story, time needed to build and test the stories, and product team acceptance of the stories

  • Timeframe in which the stories must be released, the cost to deliver the features to market, and product team acceptance of the stories

  • Delivering chunks of user-valued functionality, time needed to build and test the stories, and product team acceptance of the stories

  • Features that categorize the product, the time needed to complete the features, and the cost to deliver the features to market