Question 13
(New Update)
A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?
Select an option, then click Submit answer.
-
○
Informal communication
-
○
Internal communication
-
○
Formal communication
-
○
Horizontal communication