Question 7 (New Update)

Which of the following is an output of Direct and Manage Project Execution?

Select an option, then click Submit answer.

  • Project management plan

  • Change request status updates

  • Organizational process assets updates

  • Work performance information

Question 8 (New Update)

The purpose of inspection in Perform Quality Control is to keep errors:

Select an option, then click Submit answer.

  • in line with a measured degree of conformity.

  • out of the hands of the customer.

  • in a specified range of acceptable results.

  • out of the process.

Question 9 (Volume B)

Which output is the approved version of the time-phased project budget?

Select an option, then click Submit answer.

  • Resource calendar

  • Scope baseline

  • Trend analysis

  • Cost baseline