Question 7

Identify the Bucket Type used for Forecast entries for a month.

Select an option, then click Submit answer.

  • Weeks

  • Calendars

  • Days

  • Periods

  • Monthly entries


Question 8

ABC Corporation uses a third-party configuration tool for booking their configured sales orders and creating a configured Bill of Material (BOM). This is a simple configuration process.

However, during the Implementation of Oracle E-Business Suite, the client installed Inventory, BOM, Work In Process (WIP), Engineering, Order Management, Receivables, and General Ledger modules. The SuperUser wants Oracle to be used for creating a configured BOM when a Sales Order Is created.

What would be your recommendation in this situation?

Select an option, then click Submit answer.

  • The client has to purchase "Oracle Configurator" and install it to achieve the above requirement.

  • Use the configurator option available in Order Management, which creates the configured BOM.

  • Create a BOM with type "Configuration" when a new sales order is booked.

  • Execute the concurrent program "Populate Configuration Models," which creates the configured BOM. Schedule it to run at a set frequency.


Question 9

You learn that the planner at your client needs to make decisions on how many shifts to run on the weekend on a weekly basis. The process he or she Is currently using makes estimated capacity changes on the source system. Next, he or she runs a net change data collection, and then runs a constrained plan and reviews the results.

The planner is confident that changing the capacity and running the plan allows him or her to make a more informed decision regarding the weekend shifts; however, the process of making changes on the source system and running data collections is time consuming.

What should be your recommendation to improve this process?

Select an option, then click Submit answer.

  • Use the Targeted Refresh Data collection method to collect the proposed shift changes. Then run the Plan to provide details to make weekend shift decisions.

  • Use a Resource Group to identify the bottleneck resources. Change Plan options to calculate resource requirements for bottleneck resources. This will reduce the number of resources in the plan to analyze.

  • Change the Plan Options to Constrained - Enforce Due Dates. Use this plan to make weekend shift decisions.

  • Copy the Baseline Plan to a Simulation Plan. Make capacity changes by adding shifts using a simulation set directly In the Simulation Plan. Perform net change simulation to provide the details to make weekend shift decisions.

  • Set up Organization specific Collection Groups for Data collection to reduce the amount of data being collected from the source system. Then, run the constrained plan to provide details to make weekend shift decisions.